On the screen Planning collective leave under Company the following is available for the entire company a planning calendar which contains all the groups.
You can use this calendar to register absences that apply to everyone or to certain company groups. This avoids having to enter the information for each employee separately.
You can make this planning calendar different for one or more groups if necessary.
If necessary, you can deviate from this planning calendar for one or more groups.
As standard, a planning calendar is rolled out for the entire company. This planning calendar contains all the groups and can be found under For the entire company.
You can deviate from this and create a planning calendar yourself for one or more groups.
When you deviate from the groups in the standard planning calendar, you will no longer find the calendar under For the entire company, but under For one or more groups.
Planning Calendar for the entire company
This calendar is rolled out as standard in every dossier. The calendar contains all the groups.
You cannot remove this calendar. You cannot remove the groups in the calendar here. You can only change the details in the calendar.
1.Go to Company. 2.Click on Planning collective leave. 3.Click below For the entire company after Planning Calendar on (edit). 4.Tick a day in the calendar and use the shortcut keys under the calendar to allocate a collective absence.
You can select consecutive days at once by clicking on the first day and dragging to the last day that you wish to mark.
|
Shortcut keys
|
Meaning
|
|
PCL
|
Paid compensatory ADV leave
|
|
EU
|
Economic unemployment
|
|
A
|
Construction company compensatory leave
|
|
HOL
|
Holiday
|
|
CHOL
|
Collective holiday
This collective absence must be entered before the first wage calculation of the year.
|
|
Other
|
Select Other and choose from the list.
Example: Extra holiday for joint committee, sectoral holidays, etc.
|
4.Click Save. |
Collective leave for one or more groups
You can deviate from the planning calendar for the entire company (this calendar contains all the groups) by creating a calendar for one or more groups.
You can create a completely new planning calendar or you can create a planning calendar based on an existing calendar.
Important: You can only create a new planning calendar if you have editing rights for ALL groups.
1.Go to Company. 2. Click on Planning collective leave. 3.Click on Create after New planning calendar for one or more groups. 4.Click on Create a completely new planning and select the year from when you want the planning calendar.
Or
Click on A planning based on and select the calendar you want to use as a basis and the year from when you want the planning calendar.
Groups to which the planning originally applied will not be copied in. You have to tick them again (see step 6). 5.Click on Next. 6.Give a name to your calendar. 7.Select the Groups that are part of this planning calendar.
A group can belong to one planning calendar only! If a group is included in a new calendar, it will be removed from another calendar. 8. Fill in the planning calendar.
Tick a day in the calendar and use the shortcut keys under the calendar to allocate a collective absence.
You can select consecutive days at once by clicking on the first day and dragging to the last day that you want to mark.
|
Shortcut key
|
Meaning
|
|
PCL
|
Paid compensatory ADV leave
|
|
EU
|
Economic unemployment
|
|
A
|
Compensatory leave construction company
|
|
HOL
|
Holiday
|
|
CHOL
|
Collective holiday
This collective absence must be entered before the first wage calculation of the year.
|
|
Other
|
Select Other and choose from the list.
Example: Extra holiday for joint committee, sectoral holidays, etc.
|
9.Click on Save. 10.Confirm your change to the groups and click on OK. |
Remove planning calendar
You can only remove a planning calendar without groups.
Exception: You cannot remove the standard calendar from the dossier, even if all the groups belong to a different calendar.
1.Go to Company. 2.Click on Planning collective leave. 3.You will recognise a planning calendar that you can remove by a after the button (edit).
Click on to remove the planning calendar. 4.Click on Stop.
Important: The calendar should also be removed in the following year! See also: Removing groups in a planning calendar.
|
Removing groups in a planning calendar
Each group must /can belong to one calendar. A group that is removed from a planning calendar is automatically reallocated to the standard planning calendar.
1.Go to Company. 2.Click on Planning collective leave. 3.Click on (edit) behind the planning calendar you wish to remove one or more groups. 4.Untick one or more groups from Groups that are part of this planning calendar. 5.Click on Save. 6.Confirm your change to the groups and click on OK.
Important: The groups must also be removed in the planning calendar for the following year! |
Preparing the planning calendar for the new year
The company's collective leave days for next year must be disclosed before 15 December.
It is best to enter them in the planning calendar at the same time.
For an existing set of groups
1.Click on the pencil next to the planning calendar. 2.Change the year displayed in the top right corner to the following one. 3.At the bottom of the screen, select all collective leave days one by one in the calendar overview. Then use the shortcuts below the calendar to allocate a collective absence. Click Other if there is no shortcut for the collective absence in question. 4.Click on Save. If you have multiple planning calendars, repeat all steps until you have gone through all the planning calendars.
|
For a new group
1.Click on Create after New planning calendar for one or more groups. 2.Click on Create a completely new planning and select the year from when you want the planning calendar.
Or
Click on A planning based on and select the calendar you want to use as a basis and the year from when you want the planning calendar.
Groups to which the planning originally applied will not be copied in. You have to tick them again (see step 6). 3.Click on Next. 4.Give a name to your calendar. 5.Select the Groups that are part of this planning calendar.
A group can belong to one planning calendar only! If a group is included in a new calendar, it will be removed from another calendar. 6. Fill in the planning calendar.
Tick a day in the calendar and use the shortcut keys under the calendar to allocate a collective absence.
You can select consecutive days at once by clicking on the first day and dragging to the last day that you want to mark.
|
Shortcut key
|
Meaning
|
|
PCL
|
Paid compensatory ADV leave
|
|
EU
|
Economic unemployment
|
|
A
|
Compensatory leave construction company
|
|
HOL
|
Holiday
|
|
CHOL
|
Collective holiday
This collective absence must be entered before the first wage calculation of the year.
|
|
Other
|
Select Other and choose from the list.
Example: Extra holiday for joint committee, sectoral holidays, etc.
|
7.Click on Save. 8.Confirm your change to the groups and click on OK. |
|